For all construction projects at Program airports which must go to bid, all bids must be held until at least October 31st of that calendar year.

A description of the Governor and Council process as it relates to the AIP Grant process. Prior to grant application submittals, the following list of items shall be received by NHDOT, as applicable:

  1. Record of Negotiations
  2. Executive Order 12372
  3. DBE Plan
  4. Construction Safety and Phasing Plan
  5. Bid Tabulation with engineer's estimate
  6. Construction Award Recommendation
  7. Permits
  8. Fair Market Value
  9. Title Opinion
  10. CATEX or FONSI for NEPA Compliance
  11. SRE Calculations

Application and Submission Requirements for Project Types: